by armourvalvedev | Apr 9, 2019 | Case Studies, District Energy
Problem In order to control energy costs, a municipal building was to be connected to an existing district heating system prior to the building starting construction. To complete the connection, the local utility company would have to run two 6-inch district heating...
by armourvalvedev | Mar 1, 2021 | Case Studies, District Energy
Issue & Importance A campus district energy system was planning a small but challenging piping project. The expansion of a 3″ hot water line was complicated by a limited utility corridor, many horizontal bends, and the construction timeline of the new...
by armourvalvedev | Dec 7, 2023 | Case Studies, District Energy
Issue & Importance A district energy utility needed to connect a new building to an existing hot water main for heating and domestic hot water. The project would require 150 feet of direct buried 2” hot water service piping to be installed around existing...